Sanjha Morcha

Rs 3,800 cr spent, missiles not inducted: CAG

Rs 3,800 cr spent, missiles not inducted: CAG

Ajay Banerjee

Tribune News Service

New Delhi, July 28

The Comptroller and Auditor General (CAG) today said Rs 3,800 crore had been spent on missiles that were yet to be inducted. Half of these missiles have absorbed moisture due to wrong storage, while 30 per cent have failed tests, it has said.(Follow The Tribune on Facebook; and Twitter @thetribunechd)In its report tabled in both Houses of Parliament today, the CAG said, “The strategic missile system for the IAF in the “S” sector was to be put in place between June 2013 and December 2015. Till date, however, none of the missile systems has been installed.” In December 2010, the MoD concluded a contract with BEL for the delivery of six squadrons of this missile system. Though the CAG did not give any name, this reportedly refers to surface-to-air missile Akash and the “S” sector is a description of the eastern part of the country, including a location in the foothills of Bhutan. Akash is a medium-range SAM that travels at 3,000 kmph to hit incoming aerial threats.The CAG termed it as an “abnormal delay in the creation of infrastructure required for installation of the missile. About Rs 4,000 crore has already been spent for the purpose”.The report blames the IAF and the Ministry of Defence-owned public sector giant Bharat Electronics Limited (BEL) for the delay.The missiles were received at six IAF stations between April 2014 and June 2016, after delay of six to 18 months. The, IAF released 95 per cent of the payment (Rs 3,809 crore) by March 2016, which included creation of infrastructure like storage, workshop etc.“The strategic missile system delivered by BEL was deficient in quality”, the CAG said. Of the 80 missiles received up to November 2014, 20 missiles were test fired during April-November 2014. Six of them (30 per cent) failed the test. “Missiles fell short of the target, had lower than the required velocity, besides malfunctioning of critical units,” the CAG said.So even as missiles arrived in 2014, the infrastructure to store such weapons could not be completed at any of the six sites till October 2016.The life span of missiles is 10 years from the date of manufacturing and these have to be stored in air-conditioned environment at 23°C. Between April 2014 and May 2016, the storage was in conditions that did not have that facility. “During periodic checks of missiles, it was found that there was moisture ingress in 71 missiles,” it said.“Till the missile system is commissioned, a significant part of their serviceable life would have been over, without contributing to operational readiness and its strategic purpose,” the report said.


‘30% failed test’Of the 80 missiles received up to November 2014, 20 missiles were test fired during April-November 2014. Six of them (30 per cent) failed the test. — CAG report