Effort to support HAL has hit IAF capabilities: Dhanoa

Air chief says addl production of Su-30 is delayed by over two years

NEWDELHI: The Indian Air Force’s (IAF) efforts to support the stateowned aircraft maker Hindustan Aeronautics Ltd (HAL) has affected its fighting capabilities, Chief of Air Staff, Air Chief Marshal B S Dhanoa said in Delhi on Friday.

IAF has only cooperated with HAL; “as a service; we have made concessions for HAL, but will the enemy make any concession for us when we face them in battle?” he questioned.

The air chief was delivering the 10th Jumbo’ Majumdar International Conference at the Centre for Air Power Studies (CAPS) in New Delhi and was responding to criticism about the IAFs alleged dislike for the indigenous fighter made by HAL, Light Combat Aircraft, Tejas.

“IAF has not shifted any goal posts as alleged,” Air Chief Marshal Dhanoa said countering allegations that developments of the Tejas fighter suffered because the IAF changed specifications and requirements frequently.

On the contrary, the IAF chief said, “We have maintained the Air Staff Quality Requirements (ASQR or specifications) of the first 20 LCA Mk-I at standards issued in 1985.” And even then HAL has been able to manufacture only “10 fighters”, he added.

A HAL spokesperson declined comment on the air chief’s comments which come at a time when the state-owned aircraft maker is in financial distress of some sort and also when it is in the middle of the controversy surrounding the government’s Rafale fighter deal.

A HAL official who spoke on condition of anonymity asked: “Doesn’t IAF allow concessions and modifications to foreign vendors? Concessions are also given to Defence Research Development Organisation and the Aeronautical Development Agency. Why is HAL being singled out?.”

Putting HAL on the mat, Air Chief Marshal Dhanoa said upgrading of one squadron of Jaguar deep strike bombers, nearly two squadrons of Su-30MKi, India’s mainstay fighters, and one squadron of Mirage-2000, a multi-role fighter, all work being done by the stateowned firm, was far behind schedule. “Additional production of Su-30 is delayed by over two years and LCA production commitment (has been delayed) by over six years,” he added.

In addition, the air chief said in its quest for indigenisation, IAF has lost as many as 17 personnel including test pilots and engineers in air accidents.